The Ultimate Guide To Takt Time, Cycle Time, And Lead Time (+ Calculators)


1. What is Takt Time?


In a manufacturing or production setting, takt time is the maximal time between two successive units being produced, such that the production process can meet customer demand. Takt time is calculated by dividing the available working time by the customer demand.


Cycle time is the time it takes to produce one unit of measure. In other words, it’s the inverse of your production rate. If it takes you two minutes to produce one widget, your cycle time is two minutes.


Lead time is the total amount of time it takes to complete a process from start to finish. It can apply to manufacturing processes as well as other business processes. For example, the lead time to get a driver’s license includes the time to submit an application, take a written test, take a driving test, and receive the license in the mail.


In this guide, we’ll explain what takt time, cycle time, and lead time are, how they’re calculated, and what they mean for your business. We’ll also provide helpful calculators so you


https://unsplash.com/pt-br/@ries_bosch

https://unsplash.com/pt-br/@ries_bosch


2. What is Cycle Time?


Cycle time is the amount of time it takes to produce one unit of measure. It’s often used in Lean and Six Sigma methodologies to measure the efficiency of production processes. When cycle time is reduced, supply chain processes become faster, smoother, and more cost-effective.


Knowing your cycle time lets you keep any contractual agreements about production processes. Optimizing cycle time also helps make sure each unit produced meets quality standards, while reducing costs and increasing customer satisfaction.


Calculating cycle time is easy. Simply take the total amount of work time available and divide it by the number of product units that need to be produced. For example, if you have 8 hours of work time and need to produce 100 units, your cycle time is 8 minutes (480/100).


Cycle time can also be calculated by measuring the amount of time it takes between starting a unit of production or service and completing it.


https://unsplash.com/@robsonhmorgan

https://unsplash.com/@robsonhmorgan


3. What is Lead Time?


Lead time is the amount of time it takes from when you start a project and until it’s delivered. This could refer to the total time it takes to manufacture a product or complete a service for a customer.


Lead time takes into consideration work time, as well as any planning, transit, or other activities necessary for the end product to reach the customer. Lead times also includes lead times for components, materials, delays due to machine maintenance, and other activities.


Lead time can be calculated using Takt and cycle time. Takt and cycle time measure activities pertaining to production processes, while lead time measures the overall duration of a process.


Lead time can be used to identify the amount of time needed to deliver a certain product. This information can help in determining production schedules, managing customer expectations, and determining manpower and resource availability. Knowing the overall lead time can help businesses maximize efficiency and become more competitive in the market.


https://unsplash.com/@derekthomson

https://unsplash.com/@derekthomson


4. How to Calculate Takt Time


Calculating Takt time is relatively straightforward. The Takt time of a process is the time it takes to complete one unit, divided by the total demand for units, per a designated period of time.


The Takt time formula looks like this:


Takt Time = Available Time / Demand


For example, if you have 20 minutes of available time to produce 10 units of a product, then your Takt Time would be two minutes.


Alternatively, you can calculate Takt Time using the cycle time and number of workstations:


Takt Time = Cycle Time x Number of Workstations


To apply this formula to the example above, let's assign one work station with a cycle time of 20 minutes. In this case, the Takt Time would still be two minutes.


By calculating Takt Time, you’ll be able to determine how quickly you need to complete each unit of work in order to meet customer demand. This information can help you create more efficient processes and better manage resources.


https://unsplash.com/@jontyson

https://unsplash.com/@jontyson


5. How to Calculate Cycle Time


Cycle time is an important measurement when it comes to optimization and process improvement. It is the amount of time it takes to complete a specific process cycle, usually from the start of a task to the completion.


The formula for calculating cycle time is as follows:


Cycle Time = (Available Time x Number of Workstations) / Demand


To use our example from above, let’s assume you have 20 minutes of available time, one work station, and the demand for 10 units of work. In this case, your cycle time would be two minutes per unit.


Alternatively, to calculate cycle time you can use task duration and average task count. The formula would look like this:


Cycle Time = Task Duration / Average Task Count


If your average task count is 500 tasks and it takes 50 hours to complete, then your cycle time would be 10 minutes per task.


By calculating the cycle time of your process, you can get a better understanding of how efficient your process is and how you can improve it. With this knowledge, you can better manage resources and identify opportunities for process improvement.


https://unsplash.com/es/@goumbik

https://unsplash.com/es/@goumbik


6. How to Calculate Lead Time


Lead time is the amount of time it takes for a product or service to be delivered from the moment an order is placed to the moment the customer receives it. Unlike cycle time, it takes into account the time it takes to complete the order, not just the time it takes to complete a single process.


The formula for calculating lead time is as follows:


Lead Time = Processing + Queue + Travel


Processing is the time it takes to process an order from start to finish. Queue is the waiting time between different steps or processes. Travel is the time it takes for the product or service to be delivered to the customer.


For example, if it takes one hour to process an order, two hours to wait in a queue, and three hours to deliver, then the lead time for that order would be six hours.


By understanding lead time, businesses can more effectively plan resources and leverage it as an advantage to differentiate themselves from the competition by providing a faster service. It can also be used to better manage customer expectations and respond more quickly to customer inquiries.


https://unsplash.com/@aronvisuals

https://unsplash.com/@aronvisuals


7. The Benefits of Takt Time, Cycle Time, and Lead Time


Knowing the benefits of taking the time to calculate Takt time, cycle time, and lead time allows businesses to become more efficient and effective. Here are some of the potential advantages:


1. Set realistic deadlines: Calculating Takt time, cycle time, and lead time helps businesses set realistic deadlines that will enable them to meet customer expectations.

2. Improved customer experience: By predicting the lead time, businesses can achieve more accurate order completion forecasts and improve customer experience.

3. Reduce total costs: Making more accurate predictions when it comes to lead time can help a business reduce the overall cost by limiting the amount of resources and time that are wasted in necessary processes.

4. Monitor progress: Based on Takt time, cycle time, and lead time predictions, a business can monitor the progress of each step and make sure that the team is on task and up-to-date with the process.

5. Identify and eliminate bottlenecks: Takt time, cycle time, and lead time tells us where our workforce is most effective and applying resources. This factors in delays and bottlenecks which helps businesses identify and eliminate issues for a smoother process.


https://unsplash.com/@sonjalangford

https://unsplash.com/@sonjalangford


8. The Drawbacks of Takt Time, Cycle Time, and Lead Time


Despite the various benefits of Takt time, cycle time, and lead time, there are also some drawbacks to be aware of. Some of the cons of using Takt time, cycle time, and lead time are:


1. Can take time to complete: Calculating Takt time, cycle time, and lead time can take time and can be a tedious process. It also needs to be kept up to date to reflect the changing needs of the business.


2. Lack of customer demand: If customer demand isn’t steady, Takt time can be impacted. Predictions may not be accurate and, if resources are allocated based on these predictions, waste can occur and deadlines may not be met.


3. Inflexibility: Certain production processes may need to be flexible and unpredictable. If Takt time, cycle time, and lead time aren’t taken into account, unexpected results may occur and flexibility may be impaired.


Finally, simply calculating Takt time, cycle time, and lead time isn’t enough. Companies need to make sure that their processes can meet the calculated lead times. It is important to put processes in place and build a system that is capable of meeting customer needs with the predicted lead times. Reviewing the production cycle and ensuring that lead times are realistic is essential. It is also important to make sure that any obstacles or potential bottlenecks are met and that they are accounted for in the calculations.





For any question, please contact us in OpenTimeClock.com. https://www.opentimeclock.com.